The dynamics of float, logic, resource allocation, and delay timing in forensic schedule analysis and construction delay claims

Luận án · Tiến sĩ · năm 2009 · đề tài tham khảo

Loại tài liệuLuận án
Bậc họcTiến sĩ
NgànhKỹ thuật, xây dựng, môi trường
Tác giảNguyễn Duy Long
Người hướng dẫnGlenn Ballard; Frederick Collignon
Cơ sở đào tạoĐại học Quốc gia TP. Hồ Chí Minh
Năm2009
NguồnThư viện số Đại học Quốc gia TP. Hồ Chí Minh · trang gốc

Tóm tắt

Delay claims in construction projects present various tough and controversial issues. How to prove the three elements, namely entitlement, causation, and quantum in the “triad of proof” is an onerous task. The analyses of schedule delays and their associated damages especially concern claims analysts, project parties, courts, Boards of Contract Appeals, and so forth. On the one hand, the industry has employed various forensic schedule analysis techniques to support delay claims. Paradoxically, schedule-related factors such as float, logic, and resource allocation are frequently ignored even though they can affect project completion time and delay responsibility, too. On the other hand, the current “one-size-fits-all” methods for calculating financial consequences undermine the relative importance of delayed activities and the fluctuating nature of overhead levels. The effects of the context of a delay in terms of the timing of the delay and degree of suspension should be therefore paid attention in quantifying delay damages. Accordingly, this research develops novel techniques for analyzing causation and calculating damages in construction delay claims. They address the dynamics of float, logic, resource allocation and the delay context in forensic schedule analysis and delay claims. Several published and hypothesized case studies are used to illustrate their applications. Among other things, this research proposes: (1) an enhanced window analysis technique considering resource allocation; (2) an activity-specific overhead allocation process (ASAP) for quantifying field-overhead damages; (3) FLORA as a novel forensic schedule analysis technique that can capture the dynamics of float, logic, and resource allocation; and (4) a framework which integrates FLORA and ASAP for analyzing schedule delays and their field overhead damages in a real-time and interactive manner. Through the applications, comparisons, and evaluations in case studies, these developments really overcome various limitations of the available techniques and practices currently used in forensic scheduling and delay claims. This research recommends that the schedule-related factors should be captured in forensic schedule analysis. In addition, the quantification of delay damages should emphasize the context of a delay. This also enables equitable apportionments when concurrent delays occur. ASAP and FLORA developed in this research are able to tackle these issues.
Bản toàn văn lưu tại thư viện Đại học Quốc gia TP. Hồ Chí Minh

Thông tin và tóm tắt ở trên lấy từ kho số mở của thư viện trường. Bản toàn văn do thư viện trường quản lý — có nơi cho đọc trực tuyến, có nơi cần tài khoản bạn đọc của trường.

Mở tại thư viện trường ↗
Dùng tài liệu tham khảo cho đúng
  • Đọc để hiểu cách người trước đặt câu hỏi, chọn phương pháp, trình bày số liệu — rồi tự làm với dữ liệu và bối cảnh của bạn.
  • Ý, số liệu, bảng biểu lấy từ tài liệu này phải trích dẫn (tác giả, năm, tên đề tài, cơ sở đào tạo).
  • Đề tài trùng tên vẫn làm được nếu khác đơn vị khảo sát, thời gian hoặc cách tiếp cận — nêu rõ điểm khác trong phần mở đầu.

Hướng dẫn chọn đề tài, cấu trúc và số liệu cho ngành này: Luận văn kỹ thuật, xây dựng, môi trường · Hỏi đáp từng chương với người hướng dẫn số: Học Giả Số · Công cụ số: Luận Văn Số.

Đề tài cùng ngành

Tác giả muốn gỡ, sửa thông tin hoặc bổ sung bản toàn văn: gửi yêu cầu qua trang Liên hệ, kèm đường dẫn trang này.